Saint Mary’s Commuter Parking Lot Construction Schedule
Submitted on Wednesday, July 3, 2013
Construction work on the new parking lot area will begin on Monday, July 8. The initial schedule of activities is as follows:
Monday, July 8 – Mobilize, lay out and install temporary fencing.
Tuesday, July 9 – Strip the grass at the parking lot area and haul it away.
July 10-early August – Grading, site utilities and concrete work.
August 13 – Paving tentatively scheduled; earlier, if possible. Parking lot striping to occur the day after paving.
August 15 – Construction completed.
Note: Landscaping is not expected to be complete by the August 15 and will likely continue for several weeks after the parking lot construction is finished.
Ben Evans, Project Manager
Overaa Construction