Project management is a function within the Facilities Services Department that is responsible for updating and modernizing campus facilities.  Project managers assist with updating and improving campus facilities with the talent of in-house project team members as well as outsourced contractors and related professional services.  

Please refer to this page often for updates on the projects we have in the planning stage, scheduled, in progress, or recently completed. Projects are listed alphabetically by building. 

Status Building Project Start Date End Date
Completed Ageno, Michael

Refresh and replace renovation which includes new restrooms upgrades,

refurbished cabinetry, flooring, lighting, and window coverings. The fire

alarm system and the heating hot water boiler were also replaced. 

05/28/2019 08/23/2019
Completed Aquinas Hall Renovation of existing suite to create two new ADA rooms. 05/28/2019 08/23/2019
Completed Assumption Hall Exterior painting of the building. 08/12/2019 08/23/2019
Completed Augustine Hall Space improvements for WGE, CARE, CAPS 07/01/2019 08/23/2019
Completed Brother Cornelius Art Center Renovation of classroom / print studio. 07/01/2019 08/30/2019
Planning Brother Jerome West HVAC building automation controls.    
In Progress Cassin: 1928 Pub Addition of game room and patron/bar seating 08/15/2019 09/11/2019
Completed Dante Hall Exterior painting of the building. 07/03/2019 07/26/2019
In Progress Dante Hall 1st & 2nd Floor restroom renovations. 08/12/2019 09/09/2019
Planning Filippi Hall HVAC building automation controls. 08/12/2019 08/30/2019
Completed Galileo Hall 1st Floor restroom renovations. 07/22/2019 09/02/2019
Planning Galileo Hall New furnishings & carpet, room 201. 12/15/2019 01/31/2020

In Progress

Completed

Galileo Hall

 

Transformer replacement and tie-in (delayed)

Preparatory connection to the main electrical feed is complete.

TBD

08/20/2019 

TBD

08/20/2019

In Progress Galileo Hall/ Parking Lot Installation of EV charging stations (delayed). TBD TBD
Completed Garaventa Hall

Exterior painting of building.

06/10/2019 06/30/2019
In Progress Louis Guisto Baseball Field New Player Development Building/ Hitting Facility 08/22/2019 01/31/2020
In Progress Madigan  SAPC Phase 2: Replace tent with metal building for varsity training 09/05/2019 01/31/2020
Completed Mitty Hall Ground floor interior improvements for SOLA 04/01/2019 06/30/2019
In Progress Saint Albert Hall

Creation of space for Graduate and Professional Students

  09/30/2019
Planning Saint Albert Hall Additional group study areas on the 3rd floor 12/15/2019 01/31/2020
In Progress Saint Albert Hall Sound attenuation improvements   10/01/2019
Completed Sichel Hall Installation of HVAC and exterior door replacements 08/01/2019 08/28/2019
Completed Townhouses Roofing repairs on Freitas, Sabatte, Syufy, Thille 07/01/2019 08/28/2019
Completed Infrastructure

Gas line tie-in for redundancy